Andy J


Andy J

Andy J Under Construction

Andy J replaced two fuel tanks and had the fish hold re-worked with six seperate insulated bins. we also installed two bulkheads fore & aft as a center alley-way for generator, fabricated rails for net reel to be moved for or aft on a new aft deck.

At Dock
Deck Removed
New Bulkheads Installed
Insulating Fish Hold Compartments
Center Bulkheads Installed
Tanks Installed